The CERN Neutrino Factory Working
Group
Status Report and Work Plan
B. Autin, J-P. Delahaye, R. Garoby, H. Haseroth, K. Hübner,
C.D. Johnson, E. Keil, A. Lombardi, H. Ravn, H, Schönauer*
A.Blondel**
* This CERN group edited the
report. It is based on the work of the whole Neutrino Factory Working Group
** University of Geneva, Convener
of MUG
1 Introduction
The production of neutrinos from the decay of muons circulating in a storage ring (neutrino factory) has of late attracted considerable attention. The original interest started with the study of muon colliders [1,2]. These colliders could open the way to lepton collisions at extremely high energies. Circular electron colliders are limited in energy due to the high synchrotron radiation emitted by the electrons. Although this radiation decreases with larger radius of the accelerator, it increases with the fourth power of the energy. For this reason it seems unrealistic to build circular machines with much higher energies than LEP. The only possibility for higher energies seemed to be linear colliders with all their technical challenges. Another solution is the use of heavier leptons in circular colliders, as the limiting synchrotron radiation power at the same energy is inversely proportional to the fourth power of their rest mass. Muon beams seem to be possible candidates for this purpose. Muons can be produced by the decay of pions, which in turn can easily be produced by bombarding a target with high-energy protons. The most serious problem is the production of muon beams with the high phase-space density necessary for collider operation. In spite of some impressive progress towards this goal, no technically feasible solution has yet been found. A substantial R&D effort will be required to make progress.
With the recent confirmation of neutrino oscillations, the situation has changed drastically. High-energy muons, stored in a decay ring with long straight sections pointing towards distant detectors, provide a unique beam of high-energy electron neutrinos. This allows precise determination of several parameters of the neutrino mass matrix, possibly including the CP violating phase, which would otherwise be inaccessible. The reduced requirements (compared to a muon collider) of this neutrino factory have brought much closer to reality the concept of high intensity muon machines. The R&D effort for the muon colliders turns out to be very useful for a neutrino factory, and the increased interest from the physics side has produced a spate of activity on the accelerator side, so that considerable progress has been made towards a neutrino factory design [3,4,5]. It is interesting to note that, in turn, a part of this progress is also beneficial for the design of a muon collider.
CERN is proposing a reference scenario, which serves as guide line for its activities in this direction. With the help of other laboratories, CERN has initiated a study on some of the many technological challenges of such a facility. Discussions about the exact scope of the different collaborations are under way.
2 The basic concept of the CERN neutrino factory scenario
The reference scenario described here is based on a particular situation at CERN. It is intended as a working hypothesis that is in part CERN specific, while being dominated by the wish to achieve the required high muon fluence [26].
The requirements, as expressed in the Nufact99 workshop at Lyon [11], set a target fluence of 1021 muons per year injected into the storage ring. The present CERN accelerators are not suited to easy upgrade of the available beam power. However, a proposal [6,7] has been made to replace the CERN PS injector complex (50 MeV linac and 1.4 GeV booster) by a linear accelerator, destined primarily as injector into the PS for the LHC beam. It is intended to offer a higher brilliance LHC beam from the PS. The basic idea in proposing to build this linac is to re-use the cavities, klystrons and auxiliary equipment from LEP after this machine has been shut down. An average beam power of 4 MW appears to be feasible. We envisage in our scenario a beam energy of only 2.2 GeV, which is low, compared to other proposals. The results of the HARP experiment [9], which will measure pion production in this energy range, should produce data next year and this will be crucial in the final assessment of our choice.
A neutrino factory requires the production of beam pulses consisting of relatively short trains of very short proton bunches (nanoseconds). This allows the use of bunch rotation to reduce the large energy spread within the muon bunches. The pulse repetition rate must not be too high; otherwise the energy consumption of the subsequent machines becomes too high. Also it would be wasteful if a new injection into the storage ring took place before the previous batch had decayed (the ring design employs full-aperture kickers and so injection kills the previous circulating muon beam). The linac cannot directly provide a suitable beam; hence it will operate with H- ions and inject into an accumulator ring, using charge exchange injection to achieve a large circulating proton current. Bunches will be formed in this ring with suitable rf cavities. They will be transferred into a compressor ring for further shortening of their length. The linac will operate at 75 Hz and initial pulse duration of 2.2 ms at a mean current of 11 mA during the pulse. After accumulation and compression the resulting beam pulses, now shortened to 3.3 m s - the revolution period in the accumulator and compressor rings, contain a bunch train comprising 140 bunches spaced at 44 MHz frequency. The repetition rate is 75 Hz. It is assumed that the accumulator and compressor rings will be accommodated in the old ISR tunnel.
This beam will irradiate the production target. In the FNAL study [5] a stationary carbon target has been chosen. This has many advantages, but it is only applicable to the lower beam power assumed in this study and for the higher energy of their proton driver. In our case at 4 MW and 2.2 GeV, to ensure adequate cooling we must use a moving target. Some work has begun at RAL on the development of a moving toroidal target made out of solid material; an alternative possibility is a liquid (metal) target. Some liquid metal experience is available at CERN and we plan to investigate this option.
It is necessary to capture the pions produced in the target. The FNAL study has chosen for this purpose a 20 T solenoidal field. The solenoid magnet is expensive and needs substantial maintenance, especially when used around a target exposed to high beam power. At CERN there is considerable experience with magnetic horns, for the collection of antiprotons and in the production of (conventional) neutrino beams. It is therefore worthwhile to investigate the possibility of using a magnetic horn also for the neutrino factory.
Because of the high repetition rate and the large number of bunches,
an rf system is proposed for the manipulation of the muons after the pion
decay. The rf system will capture and phase-rotate the muon bunches, and
it will also be used in the ionisation cooling of the muon beam. Further
acceleration of the muons to 2 GeV is performed in a special linac with
solenoid focusing up to around 1 GeV, followed by more conventional quadrupole
focusing. Subsequent acceleration takes place in two Recirculating Linacs
(RLA) to an energy of 50 GeV. The muons are then injected into a storage
ring (decay ring) where they are kept for the duration of the useful beam
lifetime (1.2 ms at this energy). The muons decaying in the long straight
sections of this ring produce the required neutrino beams. A schematic
layout of this CERN reference scenario is presented in Figure 1.
Figure 1 Isometric schematic of the CERN reference scenario
for a Neutrino Factory
3 Brief description of individual subsystems of the reference scenario
3.1 The SPL Study
3.1.1 Present design
The Superconducting Proton Linac (SPL) accelerates H-
up to 2.2 GeV kinetic energy in bursts of 2.2 ms duration, at a rate of
75 Hz. The mean current during the pulses is 11mA for an average beam power
of 4 MW. For the neutrino factory the beam burst is accumulated over 660 revolutions
of the accumulator ring that transforms it into a 3.3 ms
train of 140 bunches. These are then individually reduced in length in
a compressor ring before being sent to the pion production target. Table
1 summarises some of the parameters of the SPL in this mode of operation.
Beam Current, mA |
11
|
Energy (kinetic), GeV |
2.2
|
Invariant transverse rms emittance, m m |
0.6
|
Beam energy spread (Ö 5s ) MeV |
± 2
|
Bunch length (total: Ö 5s ), ps |
24
|
Linac length, m |
800
|
rf frequency, MHz |
352
|
Overall rf power, MW |
31
|
Number of klystrons |
46
|
The beam from the ion source is bunched at 352 MHz by an RFQ and chopped at 2 MeV to minimise capture losses in the synchrotron accumulator. Conventional room temperature accelerating structures are used up to 120 MeV. Above this energy superconducting rf cavities are employed. Up to 1 GeV, new low-beta structures are needed, while 116 LEP-2 cavities in 29 cryostats are used afterwards (Figure 2).
Figure 2 Layout of the Superconducting Linac
The entire rf infrastructure and all cavities between 1 and 2.2 GeV can be built from recuperated LEP hardware, leading to a cost-effective machine. The main new elements to be constructed are:
3.1.2 Potential evolution
The design of the muon collection, cooling and acceleration is still evolving. The choice of the actual SPL characteristics is based upon the recently proposed CERN scheme [8], which defines the parameters for the 2.2 GeV proton beam hitting the target. Any evolution of the scheme will have consequences on the proton driver. The CERN HARP experiment [9] will determine the efficiency of protons of various energies for the production of pions and muons. Depending on its results, the interest of 2.2 GeV protons will either be confirmed or not. This will have important consequences for the future of the SPL proposal.
3.2 Other uses of the SPL
Although re-designed for the needs of a neutrino factory, the attractiveness of the SPL is that can replace the present injectors of the PS and improve its performance. The brilliance of the proton beam for LHC in the PS can be doubled and the maximum PS intensity can be increased by a substantial amount with immediate benefits for users like SPS in fixed-target mode (CNGS). Moreover, the present ISOLDE facility can be supplied with a beam which is up to 5 times more intense (up to 10 mA, limited by the present ISOLDE lay-out) and better matched to the target capabilities, without interfering with the PS needs. In a future stage, the next generation ISOL facility, as discussed in the new NuPECC report [31], which will need up to 100 mA, can also be accommodated.
The proton beam from the SPL may also be used for high-intensity stopped-muon physics and to produce a low-energy neutrino beam in the conventional way. A study of the interest for such a beam is being conducted in the Physics Working Group.
3.3 Accumulator and Compressor Ring
The CERN reference scenario uses the 2.2 GeV SPL (Section 3.1) combined
with an accumulator and a compressor ring that could be situated in the
ISR tunnel [27]. The ring parameters (Table 2) have followed the evolution
of the SPL study, and are now well adapted to the parameters of the 44
MHz rf muon phase rotation, cooling and acceleration section. The choice
of this rf frequency determines the harmonic number of h = 146. Consequently140
bunches (plus 6 empty buckets) fill the circumference of both rings. The
repetition rate has been chosen to be 75 Hz.
|
|
|
Circumference, m |
945
|
945
|
Beam kinetic energy, GeV |
2.2
|
2.2
|
Revolution period (b =0.954), m s |
3.3
|
3.3
|
rf harmonic number |
146
|
146
|
Number of turns |
660
|
~7
|
Repetition rate, Hz |
75
|
75
|
Figure 3 Accumulator Compressor scheme for a Neutrino Factory
Contrary to initial ideas of designing nearly isochronous lattices to economise rf voltage, both rings now feature high-gt lattices ensuring fast debunching of the very short (0.5 ns) linac microbunches as well as very fast rotation (~7 turns) in the compressor. The high gt raises the synchrotron frequency and is thus also instrumental in smoothing the accumulated distribution in longitudinal phase-space. The feasibility of H- injection (injecting 660 turns could entail intolerable foil heating) and of the final bunch rotation has been shown. Simulations including the effect of space charge on momentum compaction and of the microwave instability have not revealed any problems. Both accumulator and compressor lattices are designed; details of the intersection and the transfer between the rings remain to be studied. A schematic of the accumulator/compressor scheme detailing the bunch time structure is shown in Figure 3.
3.4 Target and Pion Capture
The contacts to the community of people and laboratories outside CERN who expressed an interest to participate in high power target and beam-dump development at the NuFact99 workshop is maintained and is being extended to new laboratories. The details of two target concepts in which either solid or liquid target-material is re-circulated in the beam are being addressed by simulations and discussions.
A number of ideas are under consideration which in principle should allow a beam power on target power of up to 4 MW. The crucial problems are mechanical movements in high magnet fields, heat transfer, material stress, radiation damage and radioactivity confinement. Laboratory tests of the simulations and determination of engineering parameters should be the next step in order to select the future directions among the many ideas around.
Equipment and expertise on liquid mercury technology exists at CERN and we believe that this is the most promising direction. Some preliminary tests of the hardware requirements for a liquid jet target, initiated as a part of the Muon Collaboration, have recently been completed [10]
Since one is interested in the production of one sign of pions for any given proton bunch, one could envisage a pion collection system based on azimuthal magnetic fields generated by a horn. A major advantage of horns is that the parts exposed to the beam are rather simple, inexpensive and can be radiation hard. The horn should be designed to focus particles emitted at large angle, and with a momentum range of 200-400 MeV/c, from a target of typically typically 2-interaction lengths. The horn design will be rather different from those used for high-energy beams, such as CNGS and NuMI, and closer to those considered for the antiproton source or the Fermilab mini-Boone beam
3.5 Muon Capture, Phase Rotation, Cooling and Acceleration
During the period September 1999 - May 2000 beam dynamics studies for the front end of a neutrino factory have been going on in the PS division. The front-end of the neutrino factory is a system that is designed to collect the pions produced in the target, to phase rotate and cool the muons and finally to accelerate the muons to 2 GeV for injection into a re-circulator.
After a first period of familiarisation with the problematic and the computer codes the beam dynamics for the following possible solutions has been explored:
3.5.1 The 44-88 MHz system
After the target the pions are allowed to decay in a 30 m long channel
focussed by a 1.8 Tesla solenoid. At the end of the decay channel the particles
with kinetic energy in the range 100-300 MeV are captured in a series of
44 MHz cavities and their energy spread reduced by a factor two. At this
point a first cooling stage, employing the same rf cavities, reduces the
transverse emittance in each plane to 60%, while keeping the final energy
constant. After the first cooling stage the beam is accelerated to an average
energy of 300 MeV. The longitudinal bunching achieved with acceleration
as well as the reduced physical dimensions of the beam allow us to employ
an 88 MHz cavity cooling system. The second 88 MHz cooling stage, mixed
with acceleration and rebunching, is continued till a sufficient number
of particles fit within a 6D invariant emittance volume defined by 15 pi
mm in the two transverse planes and 0.053 eVs in the longitudinal plane.
The first recirculator (RLA1) defines this admittance. The beam is then
accelerated to 1 GeV with 88 MHz cavities. Present calculations estimate
some 1021 muons/year (assumed to be 107 seconds of
operation) delivered to the re-circulator. The main characteristics of
the components are reported in Table 3.
|
|
|
|
|
|
|
Length, m |
|
|
|
|
|
|
Diameter, mm |
|
|
|
|
|
|
Solenoid field, T |
|
|
|
|
|
|
Frequency, MHz |
|
|
|
|
|
|
Gradient, MV/m |
|
|
|
|
|
|
Energy, MeV |
|
|
|
|
|
|
3.5.2 RF system
The underlying motivation for this set-up is to make use of hardware
with little extrapolation from existing technology. Based on experience
with 44 MHz CERN-PS cavities [14] and analysing with SUPERFISH the characteristics
of resonator geometries that could fit the needs of the muons sections,
encouraging results have been obtained. Keeping a bore radius of 30 cm,
and 25 cm around the bore to house a solenoid, a solenoid, a useful gradient
of 2 MV/m at 44 MHz is obtained with 0.8 MW peak rf power [15]. With a
similar design at 88 MHz of bore radius 15 cm, a real estate gradient of
4 MV/m is achieved at an rf power of 1.8 MW. The mean rf power consumption
to operate all the 200 m of the Rotation and Cooling sections at 75 Hz
is estimated to be12 MW.
3.5.3 Future simulation work
As a consequence of the positive outcome at NuFact00 it has been decided that the 44-88 MHz system is to be included in the present CERN reference scheme and all the available manpower for beam dynamics should concentrate the effort on a more-depth study of this system. The present simulations use ideal rf and solenoidal fields and do not yet include the material for the windows of the rf cavities, nor the necessary material for the containers of the liquid hydrogen required for the cooling. These issues need refinement of the data for the simulation programs and will be addressed in the near future.
In addition, the future beam dynamics simulation work will include:
The fundamental components of the 44/88 MHz system for phase rotation are the 44 MHz cavities. Some of the open questions are:
After the beam is cooled, the acceleration is continued using 88 MHz cavities of the same type and solenoid focusing until the beam has reached 1 GeV when a transition to 176 MHz rf and quadrupole focusing is possible. The accelerator design has not yet been optimised. In the present scheme there is no assumption of transverse emittance growth, little (a few percent) longitudinal loss and 20% losses due to muon decay. An optimisation should allow us to shorten the linac and, perhaps, shift to the higher frequency at a lower energy.
3.6. Recirculating linear accelerators
Two recirculating linear accelerators muRLA1 and muRLA2 accelerate the muon beams from 2 to 10, and from 10 to 50 GeV, respectively. Their design concept [16] has some similarities with that of ELFE at CERN [17]. Their shape is that of a racetrack. Their circumference is about 1 and 5 km, respectively. The straight sections are occupied by super-conducting linear accelerators with a peak voltage of 1 and 5 GV, respectively, consisting of LEP cavities with 7 MV/m gradient. The muon beam passes through each of them four times. The muons are accelerated on the crest of the rf wave. The transverse focusing in the linear accelerators is arranged to have constant betatron wavelength on the first pass. Spreaders at the output end of the linear accelerators feed the muon beams into four separate, vertically stacked arcs. Combiners merge the four beams into the input end of the next linear accelerator. The lattice of the arcs consists of achromats, modified such that all passes through spreader, arc, combiner and linear accelerator are isochronous.
The optical design of the linear accelerators and of the arcs is pretty straightforward and poses no particular problems. This is not true for the spreaders and combiners; in particular in the first recirculating linear accelerator muRLA1 that must handle a muon beam with an initial energy spread of approximately 8.3%. This large energy spread is one of the reasons why the number of passes is only four.
The concept of recirculating linear accelerators, operating isochronously
at the crest of the rf wave, implies that there are no synchrotron oscillations,
and that the bunch length and the absolute energy spread in the muon beam
are fixed. Hence, the relative energy spread is adiabatically damped like
1/E. The concept also imposes an upper limit on the bunch length that is
caused by the shape of the rf wave and indeed tighter than that from the
size of the rf buckets in the muon storage ring. The muon collection and
cooling systems and the linear accelerator for the muons up to 2 GeV can
meet these requirements. It remains to be demonstrated that this concept
works. The concept adopted in the FNAL study [5] is an alternative. There,
the muons are accelerated off the crest of the rf wave, the arcs are anisochronous,
and the synchrotron tune does not vanish. A list of the main parameters
is given in Table 4.
|
|
|
Injection energy, GeV |
2
|
10
|
Extraction energy, GeV |
10
|
50
|
Number of turns |
4
|
4
|
Length of linacs (2), m |
680
|
3813
|
Rf frequency, MHz |
352
|
352
|
Bending radius in arc, m |
5
|
25
|
Mean arc radius, m |
20
|
100
|
Circumference, m |
806
|
4442
|
Peak voltage gradient per linac, MV/m |
7.4
|
7.4
|
Normalised admittance, mm rad |
16.47
|
18.80
|
Normalised rms emittances, mm rad |
1.83
|
2.09
|
As is the case with the muon storage ring, the design of the recirculating linear accelerators is based on a series of assumptions concerning their engineering and the parameters of the muon beam. Once the feasibility of one or the other concept for muRLA1 and muRLA2 is established, all these assumptions ought to be questioned. If the assumed accelerating gradient was higher than 7 MV/m, the circumference of muRLA1 and muRLA2 would reduced almost in proportion, and so would be the decay losses. In the present design, about 77% of the muons survive through muRLA1 and muRLA2. However, the length of muRLA1 is chosen according to another criterion: such that the muon beam fills the recirculator, i.e. so that the muon revolution period in the RLA1 is the same as the proton revolution period in the compressor ring. This facilitates the beam loading compensation based on the beating of two sets of rf cavities with slightly different frequencies.
3.7. Muon storage ring
A design [18] was completed for a muon storage ring that fully meets the requirements of the Neutrino Oscillation Working Group, i.e. 50 GeV muon energy, 1014 muons/s arriving in the storage ring for 107 s/year. A list of the main parameters is given in Table 5. The machine has the shape of an equilateral triangle with rounded corners. It has two long straight sections feeding neutrinos to detectors at 1000 and 3000 km distance with a muon beam divergence of less than 0.2 mr. A third long straight section closes the machine and is used for tuning. The machine is installed in a plane that is inclined such that the pitch angles in the long straight sections are: -78.9, -237.9 and +319.6 mr. The triangular shape fixes the relative directions pointing towards the two detectors. Small deviations from the assumed shape are easy. Large deviations are undesirable because they imply steeper slopes.
Several tens of thousand muons were tracked for the full muon lifetime.
Collimators at 3rms beam radii in almost all quadrupoles limit the physical
aperture. Muons with initial offsets 2.4 rms beam radii in both horizontal
and vertical directions survive. A dynamic aperture problem caused by the
fringe fields of six quadrupoles was overcome by doubling their length
[19]. The long straight sections should contain the smallest possible number
of active components. One possibility is to use permanent-magnet quadrupoles
[23]. The average energy deposition around the circumference of the muon
storage ring, due to decay electrons, is about 140 W/m. Its enhancement,
caused by electrons originating in the long straight sections and getting
lost at the beginning of the arcs, has been investigated [29,21]. Two extreme
possibilities for the removal of the heat due to decay electrons, about
70 kW in a straight section of 500 m length, are a shielded vacuum chamber
with water cooling at room temperature or a transparent vacuum chamber
and regularly spaced, water cooled absorbers.
Design momentum, GeV |
50
|
Muon fluence, s-1 |
1014
|
Configuration |
Triangular
|
Normalised beam divergence in SS at se, mrad |
0.1
|
Normalised beam emittance (se),mm rad |
1.67
|
Aperture limit |
3 se
|
Relative rms momentum spread |
0.005
|
Bunch spacing, mm |
851
|
Dipole field, T |
6
|
Total length of straight sections, m |
1500
|
Average radius in the arcs, m |
46
|
Circumference, m |
2075
|
A muon storage ring with the shape of a symmetrical bow-tie [22] and long straight sections also feeding neutrinos to detectors at 1000 and 3000 km distance with a muon beam divergence of less than 0.2 mr was also studied. Its parameters are close to those of the triangular machine. The bow-tie shape has some advantages in terms of site layout and flexibility of orientation. It is the form that has been used in the schematic neutrino factory depicted in Figure 1.
According to the CERN survey group, the survey and alignment is possible at the required accuracy of 10-5 rad for aiming at the far detectors. This accuracy can be achieved, provided that vertical shafts near the ends of the long straight sections allow transferring GPS coordinate readings from the surface of the Earth into the tunnel. These shafts are needed anyway for a variety of reasons.
The beam optics of the muon storage should only be studied further, once the results of the engineering and beam parameter studies provide enough guidance. At some point, the question should be addressed what diagnostic equipment is needed, and where, in the muon storage ring.
4 Alternative Solutions
4.1 Proton Driver Rings -- Design Strategy and Reference Scenario
In view of the uncertainty of some crucial specifications like pulse repetition rate, a number of 4 MW proton driver scenarios have been studied. From these studies emerged the Reference Scenario described in Section 3. Here we mention the alternative proton driver scenarios that have been studied:
Collaboration with RAL was established for the design of a site-independent synchrotron driver scenario. 5 GeV, 50 Hz and 15 GeV, 25 Hz machines were investigated, the latter using the ISR tunnel. Each one requires two booster and two driver rings. Lattices have been designed and the H- injection and final bunch compression have been studied and shown to be feasible. The 180 MeV, 56mA H- linac is very similar to the existing ESS design and has been appropriately adapted. The study of this scheme is being pursued at RAL [28].
In the case that a slow repetition rate will ultimately be needed, we opted for a 30GeV, 8Hz configuration, using the ISR tunnel for the driver [29]. This high beam energy allows injection into the SPS above its transition energy, thereby holding the promise of an intensity increase for the LHC and for fixed-target physics. The high-gt lattice of the latter provides naturally short bunches without compression. The feasibility of the approach has been demonstrated by tracking studies including high-Q longitudinal impedances of resonance frequencies up to the pipe cut-off. The lattices designed so far are no standard types and need refinements, and it is likely that the extraction energy has to be reduced to 25 GeV, still useful for the SPS. The 2.2 GeV booster ring delivers 440 kW beam power at 50 Hz and would upgrade ISOLDE.
4.2 Pion capture
As mentioned in Section 2, the alternative scheme for pion capture after the target replaces the magnetic horn by a high-field solenoid. This has been the solution adopted in all previous studies. Since it has been studied in more detail than the solution with a magnetic horn, the simulations of the 44/88 MHz muon capture and cooling scheme are based at present on data from pion production and capture in a 20 T solenoid.
5 Proposed R&D
Herewith is a non-prioritised list of R&D topics that are associated with this CERN reference scenario. A forthcoming task is to order these topics into a programme of work on a CERN, European and World basis.
5.1 SPL
All equipment should be studied to prepare for the design of the SPL. In terms of priority and taking into account the developments in other laboratories, the most important ones are:
5.2 Target
Most of the work is at present being done in the US and at the following European laboratories outside CERN:
Their first task would be to produce a conceptual design of the whole target area by addressing the need to combine operation of the target and collector with the disposal of the high-power, spent primary beam. In addition a detailed R&D programme can be started. It would tackle the following issues:
Several major questions are unanswered by the preliminary studies performed at the occasion of the NuFact99 in Lyon [11].
5.5 44/88 MHz scheme
Design of 44 MHz cavity and of 88 MHz cavity for 44/88 MHz scheme
The performance of the overall scheme, as well as the construction (physical length) and operating costs (electricity consumption) depend heavily upon the characteristics of the rf systems. Since these systems operate in unconventional conditions, R&D is especially important. Consequently, the following topics must be worked upon in the near future:
5.6 Basic rf tests
Design of 200 MHz Nb sputtered Cu cavity (transforming existing 352 MHz LEP cavities). This is relates to the muon linear accelerator and, to beam loading problems in RLA1, since beam loading is reduced at lower rf frequencies due to the higher stored energy.
5.8 Recirculating linear accelerators
As is the case with the muon storage ring, the design of the recirculating linear accelerators is based on a series of assumptions concerning their engineering and the parameters of the muon beam. Once the feasibility of one or the other concept for muRLA1 and muRLA2 is established, all these assumptions ought to be questioned. If the assumed accelerating gradient was higher than 7 MV/m, the circumference of muRLA1 and muRLA2 would reduced almost in proportion, and so would be the decay losses. In the present design, about 77% of the muons survive through muRLA1 and muRLA2. Note that the reduction of the muRLA circumference may be undesirable for beam loading compensation considerations.
5.9 Muon storage ring
The design of the muon storage ring [18] is based on a number of assumptions concerning its engineering and the parameters of the injected muon beam. The next steps should put these issues on a firm ground. For the arcs, engineering concepts for all magnets should be developed.
It has become evident recently that beam tests of the most critical elements are needed for development of credible neutrino factory designs, in particular for the muon capture and cooling sections. An international working group is set-up to investigate the needs (energy, time structure, beam size, available testing area) and possibilities of muon test beams. From the CERN side, an evaluation of possible muon beams is undertaken, including reshuffling of a former neutrino beam line, from which a moderate intensity pulsed muon beam could be obtained. The international working group is expected to give a first report at the end of 2000. This is a place of choice for international collaboration, as muon beam lines are few and expensive, and it is not evident that appropriate ones exist now.
At the same time the instrumentation necessary to commission and run the aforementioned beam tests as well as the neutrino factory itself must be designed. Mini-workshops are taking place to define what parameters need to be measured, how and with which precision. The size and cost of the prototypes to be tested will depend on the outcome of these studies.
5.11 RAL Muon Scattering Experiment, MUSCAT, at Triumf
Ionisation cooling is now a feature of all current neutrino factory designs based on muon rings. The ionisation cooling process is a balance between the cooling effect of the energy loss and a heating effect due to multiple scattering. The studies performed so far on this balance and on the entire cooling procedure have relied on theory to determine the effect of multiple scattering, as there are no directly relevant measurements to use. The most applicable data comes from measurements of the scattering of 2.7 MeV/c electrons made over 55 years ago. This suggests that the scattering at high angle may be two times bigger than Moliere theory for light materials. Given the importance of ionisation cooling to the muon collider and neutrino factory projects, it is crucial that measurements are made with muons of approximately the correct momentum and compared directly with the theory being used in the simulations.
The purpose of the MUSCAT experiment [25] is to measure the angular
distribution, in one dimension only, of muons scattered in various low
Z target materials. For a detailed comparison with theory, this will be
done at a number of different momenta for at least one of the materials.
The targets to be used are liquid hydrogen, lithium hydride, lithium, beryllium,
aluminium, and, if time allows, steel. These will be of a thickness to
give a mean multiple scattering angle of about 10 mrad, i.e. about 10 cm
of liquid hydrogen and a few mm or less of the other materials. The angular
distribution will be measured up to about 34 times this value. The
first experimental run took place during June/July 2000. A second run is
being planned and mini-cooling extension to the experiment is under discussion.
CERN is collaborating in this experiment.
CERN Reference Scenario parameter list
|
||||||||||
Mean Beam Current during pulse, mA |
|
|||||||||
Energy (kinetic), GeV |
|
|||||||||
Invariant transverse rms emittance, m m |
|
|||||||||
Beam energy spread (Ö 5s ) MeV |
|
|||||||||
Bunch length (total: Ö 5s ), ps |
|
|||||||||
Linac length, m |
|
|||||||||
rf frequency, MHz |
|
|||||||||
Overall rf power, MW |
|
|||||||||
Number of klystrons |
|
|||||||||
|
||||||||||
. |
|
|
||||||||
Circumference, m |
|
|
||||||||
Beam kinetic energy, GeV |
|
|
||||||||
Revolution period (b =0.954), m s |
|
|
||||||||
rf harmonic number |
|
|
||||||||
Number of turns |
|
|
||||||||
Repetition rate, Hz |
|
|
||||||||
|
||||||||||
. |
|
|
|
|
|
|
||||
Length, m |
|
|
|
|
|
|
||||
Diameter, mm |
|
|
|
|
|
|
||||
Solenoid field, T |
|
|
|
|
|
|
||||
Frequency, MHz |
|
|
|
|
|
|
||||
Gradient, MV/m |
|
|
|
|
|
|
||||
Energy, MeV |
|
|
|
|
|
|
||||
|
|
|
||||||||
Injection energy, GeV |
|
|
||||||||
Extraction energy, GeV |
|
|
||||||||
Number of turns |
|
|
||||||||
Length of linacs (2), m |
|
|
||||||||
Rf frequency, MHz |
|
|
||||||||
Bending radius in arc, m |
|
|
||||||||
Mean arc radius, m |
|
|
||||||||
Circumference, m |
|
|
||||||||
Peak voltage gradient per linac, MV/m |
|
|
||||||||
Normalised admittance, mm rad |
|
|
||||||||
Normalised rms emittances, mm rad |
|
|
||||||||
|
||||||||||
Design momentum, GeV |
|
|||||||||
Muon fluence, s-1 |
|
|||||||||
Configuration |
|
|||||||||
Normalised beam divergence in SS at se, mrad |
|
|||||||||
Normalised beam emittance (se), mm rad |
|
|||||||||
Aperture limit |
|
|||||||||
Relative rms momentum spread |
|
|||||||||
Bunch spacing, mm |
|
|||||||||
Dipole field, T |
|
|||||||||
Total length of straight sections, m |
|
|||||||||
Average radius in the arcs, m |
|
|||||||||
Circumference, m |
|
Acknowledgements
The present work is the result of the effort of the Neutrino Factory Working Group. The Working Group comprises staff of CERN and other European laboratories and institutes. CERN is in contact with BNL, CEA, Cornell, FNAL, FZJ, GSI, INFN, IN2P3, KEK, LBL, PSI, RAL and TRIUMF for present and possible future collaborations. This external help has already been extremely valuable and will be essential in the future to succeed with the proposed R&D activities. The support of ECFA is gratefully acknowledged. The copy editor was CDJ.
References